South Stream Serbia – South Lot – Pre-commissioning Campaign

Turkstream Extension pipeline hydraulic test campaign in Serbia, from Bulgarian border in Zaječar to Žabari.

Engineering, procurement and rental of materials and equipment, pre-commissioning flooding, cleaning and gauging, hydraulic testing, dewatering, drying and safety coordination during operations.

Total length 147 km, diameter 48”, DP 75 bar, including BVS and two measuring stations.